May 2021 Update

Greetings brothers and sisters of Canyon Ridge Church! We are excited to share with you an update on the ministries and construction of Iglesia del Nazareno de Santa Maria.

During the last 60 days, we cut and bent steel to assemble the concrete footing. Once the footing was poured, we proceeded to assemble the columns and once the columns were poured, we started with the chaining in preparation for the slab-pouring. 

We continued to carry out Bible study activities once a week on-site, with biosecurity measures, and also through social networks and the zoom platform. 

Due to the rainy season, it was difficult to transport the construction material because the road was in poor condition, and the dump trucks got stuck in the middle of the road. Thank God, despite these circumstances, we were able to move forward with the construction. 

In the next 60 days, we plan to pour the slab, raise the pillar and wall of the first floor and pour the bleachers. 

I am very grateful to God and my sponsor for all the support I receive. In the project, I feel protected, loved, and known, and my family is very appreciated by the brothers of the Church, so I think is a great blessing for me and my family to have the construction of the church and the classrooms so that my little brothers and I can learn much more. I am also glad that not only me but also my neighbors, will have the opportunity to go to Church. Thank you very much for your help! 

Rudy Salazar